Grid-charged MW-scale BESS
1.25 MW / 5 MWh · 440 V three-phase
A modular 5 MWh LFP battery behind ten paralleled 125 kW bidirectional PCS modules (1.25 MW). TOBOR EMS schedules grid charging and discharging through the same PCS path, and on grid failure the isolated 440 V load bus is supplied from the battery through a 400 / 440 V voltage-matching interface.
How the energy moves.
Conceptual single-line diagram · grid charging / grid discharging | TOBOR EMS | 1.25 MW / 5 MWh | 440 V three-phase
Scroll the diagram sideways →
Concept only. Single lines represent power circuits. Final conductor sizes, protective-device ratings, transformer capacity, neutral / earthing arrangement and transfer sequence require engineering approval. Net 1.25 MW output and four-hour backup must account for losses, reserves and site conditions.
Grid charging / discharging
- Charge: grid → AC bus → interface → PCS → battery.
- Discharge: battery → PCS → interface → AC bus → grid / loads.
- TOBOR EMS sets charge, discharge and export limits.
Grid unavailable
- Grid isolation opens; the utility is disconnected.
- Battery → PCS → voltage-matching interface → load bus.
- BESS supplies the 440 V three-phase loads.
Technical specification.
Power conversion
- PCS10 × 125 kW bidirectional modules in parallel
- Aggregate PCS1,250 kW nominal at unity PF
- System interface440 V L-L · 3-phase · 50 Hz
- Voltage matchingBidirectional 400 / 440 V transformer
Battery
- Nominal energy5 MWh (5,000 kWh)
- CellLFP · 3.2 V · 314 Ah
- Cycle life7,000–8,000 cycles*
- Indicative backup5,000 kWh / 1,250 kW = 4 h ideal
Scope & protection
- BatteryRacks / enclosure with BMS · thermal management
- SafetyFire detection / protection
- SwitchgearAC/DC switchgear · grid isolation · energy metering
- ControlTOBOR EMS · grid charge / discharge · export limit
Design-basis values from a TOBOR project offer. *Cycle life depends on cell OEM specification, depth of discharge, temperature, C-rate and end-of-life criterion. Final ratings, certifications and performance guarantees follow the approved project-specific design.
- Industrial plants on 440 V buses wanting backup and peak management
- Time-of-day tariff shifting with export-limited discharge
- Replacing large DG sets on critical process loads
- Solar developers and EPCs packaging storage for C&I clients
Want this design at your site?
Tell us your vehicles, loads and grid connection. Our engineers adapt the design and send a single-line diagram with the offer.